Ryan Civil Contracting were engaged to complete the stormwater works on this project. Due to the nature of the sandy conditions at the Port of Brisbane up to 60% of this drainage was completed under the water level. Ryan Civil Contracting employed the use of Well point dewatering and spearing as a means to dewatering in order to safely and productively install the stormwater drainage.
Project Summary
- 1.6km of stormwater drainage
- Pipe sizes from 1200 to 225
- Pipe depths up to 3.5m deep
- 35 stormwater pits
- 1km of wellpoint dewatering and spearing utilised to dewater works
- Sheet piling and trench boxes utilised for shoring requirements
- Bio retention basins
LOCATION: Bishop Drive, Port of Brisbane
CLIENT: Hansen Yuncken Pty Ltd
DATE: January 2015