Project: TNT Logistics Facility

Location: Redbank Motorway Estate 

Client: Qanstruct (Aust) Pty Ltd

Date: October 2014  

Project Description: This project consisted of an 80,000m2 commercial development. Ryan Civil Contracting were engaged to complete the entire bulk earthworks, drainage and pavement preparation for this project. 

Project Summary: 

  • 8,500m3 topsoil to tip 
  • 20,000M3 cut to fill 
  • 15,000M3 cut and haulage offsite to tip 
  • 1.6km of stormwater drainage varying from 1,200 – 225mm pipe size and depths up to 4.5m 
  • 62 stormwater pits 
  • 72,000m2 subbase preparation for concrete slabs 
  • 70% of works completed within 6 weeks of project mobilisation 